PARK IMPROVEMENTS
2012 - New irrigation and drainage system - Work was funded by the Parks Improvement Bond Measure, approved by the citizens of Tacoma in November of 2005.
Project Manager: Ron Peart, (253) 591-5295
2012 - Shelter building is completed.
2011 - Performance Stage was installed. This project was funded by the Old Town Business & Professional Association ($87,000).
2010 - New playground, half basketball court, walkways and site furniture were installed. Design was by AHBL and contractor was Dumpman construction. Work was funded by the Parks Improvement Bond Measure, approved by the citizens of Tacoma in November of 2005.
Project Manager: Kristi Evans, (253) 305-1054
2009 - Old Town Park Design Plan created to guide future improvements to this park.