Project manager:
Kristi Evans, Project Manager, 253-305-1054
About this park:
Discover Parks
Park land acres: .54
| Schematics |
| Photo Gallery |
| History of this park |
Sawyer Tot Lot
| Location |
| What's Planned for Your Park |
| Budget |
(2006 - $25,000 / 2007 - $165,000)
| Project Status |
![]() |
![]() |
| Sawyer Tot Lot Before | Sawyer Tot Lot After |
03/05/08 Project completed.
01/18/08 The contractor is still waiting for two small pieces of fencing.
12/07/07 Project is substantially complete. Fencing is on order and anticipated by 12/10/07.
10/12/07 Fence materials are available and final fence work should be installed next week.
09/28/07 While project is substantially complete, access to the park is blocked by contractor fencing to allow grass to grow. Also, the contractor is still waiting for delivery of ornamental fences which were supposed to have shipped 09/06/07.
08/03/07 The contractor is completing final items. Seeding is planned for Sept. for better establishment.
07/20/07 All playground equipment has been installed.
06/08/07 Play equipment should be delivered next week.
05/25/07 Work is 50% complete. Work will be completed by August.
05/11/07 The old play toys have been demolished.
04/30/07 KBH Construction have been given the "notice to proceed" with playground upgrades at Celebration Park, Lots for Tots, Puget Park and Sawyer Tot Lot. The work is to be completed by August 28th.
03/16/07 Bids were received on Feb. 27, 2007. The Construction Contract will be brought to the Board at their March 26, 2007 meeting.
11/09/06 Staff has met with community groups. A consultant contract for final design has been established and notice to proceed has been issued.
| Schedule |
• Begin public meeting outreach - June 2006
• Design - September 2006
Design consultant is DDLA
• Completion of Construction & Bidding Documents - December 2006
• Construction - February 2007
B & H Construction
• Completion - September 2007
| Community & Board Participation |
- Upcoming Community Meetings
- Completed Community Meetings
– Aug. 24, 2006 - discussion of ideas for playground equipment and other improvements
– Sept. 26, 2006 - review of drawings and cost estimates for the preferred equipment and prioritization of the other improvements - Events
- Board Meetings & Resolutions
Board Meetings
Board Capital Improvement Committee
Find out more about the Board of Park Commissioners. - Metro Parks' Public Participation Policy.
- Send us your comments about this project.
Last Updated: Jul 23, 2008 5:12 PM