Metro Parks Tacoma

  • Park Finder
  • Register

Project Updates

Capital Projects Update – August 2018

Partnership Initiatives

  • Eastside Community Center
    Metro Parks is working with Tacoma Public Schools, the City of Tacoma, Tacoma Housing Authority, Boys & Girls Clubs of South Puget Sound, and the YMCA of Pierce and Kitsap Counties to develop a new facility to meet the needs of the Eastside community. We’ll have more updates in the months ahead.
    Status: In the month of August, we will hit the projected substantial completion date. Much of the interior work will be finished. The pool is going through its finishing stages (plaster, installation of all toys, testing of systems
     
  • Prairie Line Trail
    Metro Parks is coordinating with the City of Tacoma for an extension of the urban trail that follows the former Prairie Line Rail corridor from South 23rd Street through the UW Tacoma campus and extending to Dock Street along the Thea Foss Waterway. This phase will complete the trail from Pacific Avenue to Dock Street.
    Status: The City is in the right-of-way phase of finalizing easements and is scheduled to bid after the first of the year.

Point Defiance Park Projects
(see DestinationPointDefiance.org for more information about Waterfront Phase I and the Master Plan Update)

  • Point Defiance Park - Waterfront Phase 1
    Complete the public pathway from Point Ruston to Point Defiance Park with a new trail and bridge over Pearl Street. Provide a new location for boat and trailer parking to support the existing boat launch. Finish the remediation work at the Point Defiance peninsula and establish a new park on the peninsula land.
    Status: Trail: Grading is largely complete and hardscape installation will continue into August.
    Peninsula: The park pavilion building and its surrounding hardscape are the major peninsula items left to complete. The peninsula buildings are waiting on doors and then will be complete. The third building will begin construction once the parking lot below the soil nail wall (Lot A) is complete (August). Bridge: Largely complete. Not yet substantially complete. Landscape installation to be completed fall 2018, including the hillside repairs which are underway.
     
  • Point Defiance Park -– Roundabout
    Design and build a roundabout at the entrance to Point Defiance Park, while updating the intersection at 51st & Pearl and providing a bike lane from 51st to 54th.
    Status: Project has reached substantial completion and has only minor scope items remaining to reach final completion.
     
  • Parking and Circulation Study
    This is a full comprehensive study for the vehicular, pedestrian, and bicycle traffic circulation and additional parking at Point Defiance Park. After study is completed, will be presented with alternatives for additional parking and improved circulation.
    Status: The final Parking & Circulation Study has been submitted. The design scope of work is complete and waiting on final approval confirmation.
    .
  • Japanese Garden Design
    In cooperation with Tacoma’s sister city Kitakyushu, this project will reconstruct the Japanese garden in front of the Pagoda in the traditional style. This phase will complete the design as we work with Japanese Garden Designers from Japan.
    Status: On hold pending final recommendations of Shared Use Trail system under Point Defiance Parking and Circulation Study as this influences final design of the Japanese Garden Expansion design.
     
  • Green House Relocation
    Relocated greenhouse production operations to the Tacoma Landfill.
    Status: Project is in closeout, retainage being issued August 2018.
     
  • Boat Lift Improvements
    Improvements will be made to the grates, guide beams, lift enclosures, switches and other improvements as a result of the inspection/design process.
    Status: Structural work complete for all 3 lifts, Lift #1 operating with current electrical components.  Electrical work on-going for lifts 2 & 3.  Pending L&I inspection, Lift #2 and #3 will come online and Lift #1 will go down for electrical work.
     
  • Point Defiance Owen Beach Improvements
    Site improvements at Owen Beach that include new restroom building, renovation and addition of new shelter, new playground, kayak launch and beach accessibility, parking, landscaping and walkway improvements.
    Status: Revisiting sea level rise and building placement before starting Design Development. Had pre-permitting meeting with City of Tacoma.
     

Point Defiance Zoo & Aquarium
(also see the zoo’s capital projects page for more information)

  • New Aquarium
    Design and construction of a new aquarium to replace the aging North Pacific Aquarium.
    Status: Most work is complete, with art install August 20-21 for Glass Jelly and August 13- 17 for Shoal & Shimmer.
     
  • Picnic Shelter
    Construct a picnic shelter to be placed in the location where Point Defiance Zoo & Aquarium currently sets up tents for this purpose every summer. This is to be a permanent structure.
    Status: Landscape around the building slab will be completed by July 1, in time for the summer season. As done in the past, a tent will be placed on the slab for picnic use until the contractor comes back in October to erect the building on the slab. 
     
  • Polar Bear Exhibit
    This exhibit opened in 1982 as part of the Rocky Shores/ Arctic Tundra Exhibit. It won the AZA Exhibit of the Year Award in 1983. This project is a significant upgrade and renovation to this historic exhibit.
    Status: Project cancelled

Other Highlights from Neighborhood Council Areas

New Tacoma

  • W.W. Seymour Botanical Conservatory Restoration and Expansion
    Renovation and expansion of the conservatory. Steering committee formed and schematic design is underway.
    Status: Project is complete. Applied for a State Historical Heritage Grant.
     
  • W.W. Seymour Botanical Conservatory Restroom
    Design Development through construction of a restroom connecting to the existing conservatory.
    Status: Tiling, painting, epoxy flooring, storage yard paving are completed. Waiting on glass gasket and metal work delivery.
    .
  • Foss Waterway Parks
    In collaboration with the Foss Waterway Development Authority this project includes the design for two park sites along the Foss Waterway including a new boathouse facility for kayaks and shells.
    Status: Staff working on programming at Waterway Park, plus there will be further user group surveys sent out.  Ballard Kings next task is a ProForma. Central Park’s 100% Design Development is due the firsts of August for review.  Pre-permit meetings have taken place.  RCO local parks grant presentation happened August 13, 2018.
     
  • Neighbors Park
    Play court resurfacing and ADA access.
    Status:  Will be completed under Phase 2 of the Districtwide Court Improvement project in 2018.
     

North Tacoma

  • Dickman Mill Park Expansion & Head Saw
    An extension of the existing Dickman Mill Park. This is to restore and publicly display the historic Head Saw and provide plaza space with expanded decking for viewing.
    Status: Art brief is in the review process. 100% Design Development Drawings complete and in review. Looking to submit some environmental permitting in August.

South Tacoma

  • Meadow Park Facility Improvements
    Identification and implementation of improvements, including irrigation control and upgrades to the restrooms, restaurant and pro shop.
    Status: The Driving Range and smaller associated buildings (Ball Shed & Teaching Studio) reached substantial completion in May. We are awaiting coordination with PSE to complete the work. This is anticipated in August 2018. In the fall, the final improvements to the clubhouse (structural and ADA upgrade) will be bid out.
     
  • Meadow Park Hole #13 Bridge Improvements
    Structural Analysis of Bridge, Bridge Improvement Design Recommendations, Survey Baseline establishment for bridge monitoring.
    Status: Design drawings and cost estimate scheduled for August 17, 2018, with bidding and construction set for January through March 2019.
     
  • Oak Tree Site Upgrades & Art Project
    Implementation of Development Plan to include new parking lot and seasonal restroom shelter, tool storage shed, trail and path upgrades, site furniture, tree removals, prairie expansions and native plantings to support Oak habitat,  new nature playground, park ID and wayfinding/ interpretive signage. After the city completed the Prairie Line Trail, Metro Parks Tacoma will provide restoration to two adjacent areas to the trail (pump house parking lot, gravel pit and partnering with the COT with an art project).
    Status: SEPA review is underway, with deadline for comments August 17, 2018. Bidding expected to start in August 2018 and construction in September 2018.
     
  • South Park
    Play court resurfacing and ADA access.
    Status: Will be completed under Phase 2 of the Districtwide Court Improvement project in 2018.
     

South End

  • Wapato Park – Dock Replacement
    This will replace the two wooden dock structures for improved access and paddleboat/ kayak launching and events.
    Status: Project is complete. 
     
  • Charlotte’s Blueberry Park Garden/Playground
    Design of community garden/park amenities. Continuation of public process to address possible addition of playfield, trails, and/or wetland enhancement.
    Status: Working on final construction punch list.
     
  • Verlo Playfield
    Basketball court resurfacing and ADA access. ADA access to tennis court, consider alternative use for tennis court area.
    Status: Will be completed under Phase 2 of the Districtwide Court Improvement project in 2018.
     
  • Stewart Heights Park
    Court improvements.
    Status:
  • Construction started in August.
  • Swan Creek Phase II - Master Plan Update and Construction
    Update masterplan and pursue conditional use permit
    Status: The first steering committee meeting is May 24. The topographic survey is being produced and getting ready for cultural resource study.
     

North East

  • Browns Point Lighthouse
    Accessible pathways and promenade, additional parking, new furnishings.
    Status: Park to re-open mid-August.
     
  • Browns Point Playfield
    Basketball and tennis court reconstruction due to large cracks, improve ADA parking and access route to basketball courts.  Make necessary improvements to play equipment.
    Status: Consultant working on Permit Drawings. Design and permitting this Fall/Winter 2018 and construction starts Spring 2019.

Central

  • Tacoma Nature Center Building and ADA Improvements
    The scope of work includes ADA upgrades and improvements to the entry ramp, and entry door; relocation of a utility pole at Discovery Pond; replacement of exterior wooden stair treads; and utility routing to Coyote Flats. There will also be minor site and signage upgrades on the TNC property and a Facility Assessment to the main building. Dependent upon the result of the facility assessment, the scope of work may shift to address needs at the main building.
    Status: SOQs have been submitted and under final review to develop construction and permit documents to improve and upgrade a failing exterior envelope (roof, windows, siding, doors, and exterior landings) of the main TNC building.

West End

  • Titlow Lagoon Design and Phase 1
    Provide matching funds for lagoon restoration in accordance with partnering agencies.
    Status: Geotechnical investigation completed in June 2018: Borings up to 80 feet deep on either side of the existing lagoon culvert were drilled and ground penetrating radar was completed along the BNSF right-of-way.
     
  • Titlow/Hidden Beach Improvements
    Hidden Beach and natural area trail/path/beach access upgrades. Landscaping enhancements, natural area restoration, demolition of shelter and old restroom at Hidden Beach. Utility modifications at former TOA facility. Remove or perform bridge retrofits to TOA Railroad bridge.
    Status: Topographic and Boundary Survey complete. Titlow Park Master Plan Update second public meeting to be held this fall
     
  • Titlow Garage
    Renovation of existing shed building adjacent to Titlow Lodge to better serve the needs of parks operations and maintenance team.
    Status: Project will be publicly bid through the Small Works Roster in August 2018. Construction will occur after the summer camps are completed, in late-August/early-September 2018.

Completed Projects:

PDF Versions: